RE-ORDERING & REFURBISHMENT TO ST MARY'S CATHOLIC CHURCH, HERRINGTHORPE
POSTED: 20/7/2011
Summary
Client: The Diocese of Hallam
Principal Contractor: G Wilkinson Construction Ltd
Project Cost: £187,000.00 plus VAT
Timescale: 12 weeks
Brief
As part of an ongoing programme of maintenance and refurbishment works to the site, the church building was refurbished internally in June 2009. The brief was to provide for improvements to the heating, lighting and sound systems together with uplifting the internal appearance cosmetically.
Proposals
The works included for a new suspended ceiling to the main body of the church and plastered ceiling generally to the side aisles, together with new carpeting, decorations and re-glazing of windows. Electrical services installations were replaced including new lighting, small power and sound systems with general upgrading to the existing heating installations.